The CAG Draft Report on the audit of
the Production Sharing Contracts for the on-shore and off-shore oil and gas
blocks is now widely being circulated in the media, showing once again the
unholy nexus between the UPA and big capital in the country.
The CAG has shown that the
Directorate General of Hydrocarbons (DGH) allowed Reliance Industries and other
private operators to gold-plate the capital costs of
the plant allowing them to make huge profits. The Production Sharing
Contract pegged the profit share of the private operators and the Government to
something called an Investment Multiplier, which meant that higher the
capital cost, the larger the share of the profits of the private parties.
The capital costs in the KG Basin
D-6 Block went up from $2.4 billion in the initial contract to $8.5 billion.
This was the pattern followed in other gas and oil fields also, involving
Reliance, Cairn Energy and others.
The
modus operandi was to submit a bid which shows a certain capital cost
and during the operation of the contract, inflate the capital cost by a huge
amount with the connivance of DGH and the Ministry of Petroleum. The Management
Committee in which the Government had 2 nominees out of 4 played no oversight
role in such inflation of contracts.
For inflating
the capital costs, the familiar route is of course over-invoice through
sweetheart deals from “friendly” sub-contractors, sometimes even a Reliance
family company. While the CAG has not computed the loss to the
exchequer, it has held that the Government has suffered
large losses on this account. It has also held that the Production
Sharing Contact being followed by the Government of
India has very little controls on the investment costs, unlike for
example, Bangladesh, where the Management Committee which has 50% Government
nominees as in India, has to approve any expenditure above $500,000.
The CAG Draft Report has also
brought out that while the contract envisaged that if the company did not
develop certain areas within the contracted area within the stipulated time, it
should have been relinquished. Instead, the DGH and the Ministry of Petroleum
allowed the whole area to be designated as “discovery area” in violation of the
contract.
As we shall show below, there are
two sets of scams that have taken place, CAG having looked at only one of them.
- One is of course various violations of the Production Sharing Contract as pointed out by CAG;
- the second is the high price of Reliance gas -- $4.2 per Million BTU (MBTU) -- set in 2007 by the Empowered Group of Ministers headed by Pranab Mukherjee.
Gold-plating Capital Costs in KG D6
Block and the role of DGH
The Gas and oil field in question is
known as KG-DWN-98/3 (Block D-6), and consists of 8,100 sq. Km. of off-shore
area in the Krishna Godavari basin. Block D-6 was awarded to Reliance
Industries (90%)and Niko Resources Ltd (10%) under New Exploration Licensing
Policy 1 (NELP-1) bidding round under a Production Sharing Contract. Initially,
the D6 was to produce 40 MMSCD (Million Cubic meters per day), which
was subsequently revised to 80 MMSCD. The initial development cost in the
contract was $2.4 billion which was revised through an “addendum” in 2006 to
$5.2 billion in the first phase and $3.3 billion in the second phase. CAG has
also observed that the $3.3 billion for the second phase has every possibility
of being hiked up in the same way as the first phase.
The Production Sharing Contract
(PSC) that the Government had struck with RIL in 2000 envisaged that there
would be something called “cost petroleum”, which would cover Government
royalty of 5%, operating costs, the costs of exploration, and the development
cost of producing gas. Till the the capital costs are recovered, 90% of the
petroleum/gas sold would be considered as “cost” petroleum and the rest 10%
would be “profit” petroleum.
The catch here is that proportion of
profit sharing changes depending on the amount of cost recovered to the total
cost, something that the contract calls as Investment Multiplier. The
proportion of shares between RIL and Government is pegged to this Investment
Multiplier. Till the major portion of the costs are recovered, Reliance gets
the major share of the “profit” petroleum. It is only after the major part of
the costs have been recovered that the Investment Multiplier begins to increase
and so does Government's share, which is pegged to this Investment Multiplier.
That is why increasing capital costs helps Reliance retain a much larger share
of the profits in the initial years, while the Government gets its share only
in the last phase, when the production starts to decline.
Reliance therefore can make a double
killing -- by over invoicing the capital costs, it can skim money from the top.
In addition, by ensuring that the capital costs take a longer time to recover,
it takes out its major share of the profit right in the beginning.
If it was only a question of getting
money later, it could be argued that Government has not suffered a loss, only
postponed its earnings. But here is the problem. In financial accounting, money
earned later has to be discounted by an amount equivalent to what we would have
earned if we had put the money in the bank and earned interest. The same amount
earned today therefore is more valuable than money earned one or more years
later. If we apply the standard discounted cash flow method – discount future earnings
by a nominal discounting rate of 10% – we find (see table below) that
Government's share would have been 63% of the total profits if the
original figures of production and and capital costs retained, while now it is
only 48%. Conversely, Reliance's share goes up from 37% to 52%.
|
|
Capital Costs
$ Billion
|
Production Volume MMSCMD
|
Total Profits
$ Billion
|
RIL's Share %
|
Gov's Share
%
|
Discounted RIL Share
%
|
Discounted Govt's Share %
|
|
Original
|
2.5
|
40
|
19.4
|
30
|
70
|
37
|
63
|
|
Revised
|
8.8
|
80
|
35.4
|
44
|
56
|
52
|
48
|
Notes:
- Calculations done by the author
- Figures based on a 12 year production period and constant gas production.
- If a 16 year period is taken and/or production figures increased, the figures would change somewhat, but the broad trends would remain the same.
If we look at the fact that the
extra investments have doubled production, how much has each of the parties
gained out of this doubling of revenue? Out of the extra revenue (at discounted
prices) of about $7.5 billion, Reliance gains about $5.5 billion and the
Government only about $ 2 billion.
The increase of four times the
capital cost for a mere doubling of production had always seemed highly
suspicious. No logic can explain why doubling of capacity to should lead to
such an increase – economies of scale normally ensures that a doubling of
capacity would increase capital cost by about one and half times. The Draft CAG
Report now makes clear that the increase from $2.4 billion to $5.2 billion took
place for the first phase, where no augmentation of capacity was involved. This
makes nonsense of the bidding procedure for awarding of blocks, as the
calculations for award of blocks involves profit shares promised by the various
parties. If the capital costs change, all this change, vitiating the award of
contract itself.
Not only did the Directorate General
of Hydrocarbons accept this increase in capital cost, which under the contract
it need not have accepted, it did so in unseemly haste – it took a scant 53
days to go through cost increase of nearly $ 6.3 billion! Some wizardry indeed.
The CAG's Draft Report brings out
the various ways costs could have been doctored – single party bids, making
changes to scope, substantial variation on orders, etc. CAG has stated that it
is going to examine these issues in greater detail in a subsequent audit.
In November 2009, preliminary
investigations by the CBI had found evidence of “gross abuse and misuse of
public office” by V K Sibal, the then Director General of DGH. This had been
informed to the Petroleum Ministry and to CVC. Numerous links had been found
between Sibal and Reliance. The CBI enquiry remains stalled, very much in the
telecom 2G mode, showing that Reliance tentacles in the Government go far
beyond Sibal.
The Curious Case of $4.2 Gas Price
An Empowered group of Ministers
(EGoM), in September 2007, set the price of gas at $4.2 per MBTU for five years
with no transparency and without giving any reason for this price. It might be
noted that in the same period, (2005-2008), ONGC was being paid only $1.8 per
MBTU. The $4,2 price was supposedly done on the basis of RIL's price
“discovery.”
Reliance's price discovery was to
ask a selected set of bidders to quote a gas price according to a formulae
which fixed the price within a narrow range of $4.54 to $4.75. With this as the
basis, Reliance declared the “discovered” price to be 4.59/MMBtu which was
later revised to $4.3/MMBtu. The Government then magnanimously decided that the
right price was $4.2 and claimed that it was arrived at through “a discovery” mechanism.
It might be argued that the
Government also gained out of the high price of gas. This is indeed true – by
our calculations, the Government stood to gain about $4 billion or about Rs.
20,000 crore from the increased price of gas as its share of profits. However,
as gas is the major feedstock for fertiliser production and also a fuel for
power, this gain has to be balanced against the resulting higher fertiliser and
power prices. If the cost of production of fertiliser and power goes up, so
does the government subsidy. So while the RIL would pocket the benefit of the
higher cost of gas, the Government would have to pay out a much higher subsidy
of around Rs. 75,000 crore for a gain of Rs. 20,000 crore and therefore incur a
net loss of more than Rs. 55,000 crore.
It is indeed strange that at a time
that the government complains about high cost of subsidies, it should itself
promote policies that help private parties while pushing up its own subsidy
bill.
Not only was the price set at a much
higher level than the cost of production, it was also set in foreign exchange
and pegged to the price of crude in the international market. Why should the
gas price be set in dollars for even the future when the costs have already
been incurred and therefore can easily be converted into rupees? Why should the
gas price be set at $4.2 when RIL itself admitted in the court proceedings
between it and Anil Ambani's RRNL/NTPC that its cost price of gas was $1.43 and
it was willing in 2004 to sell NTPC gas at $ 2.34? What is the justification of
pegging the domestic gas price to the price of crude in the international
market, to which it has no relation?
Fixing gas prices without examining
cost figures and a mechanism of converting the cost figures to a gas price is
making gas pricing another way of handing out private largesse. No basis of the
gas price rate of $4.2 has been given, so how did the Ministers pull this
figure of $4.2 – straight out of their collective hat?
Promoting RIL's Monopoly in Gas
The last issue is one of monopoly.
At the moment, Reliance is major gas producer, Reliance Gas Transportation and
Infrastructure Limited (RGTIL) owns the pipeline and again Reliance is getting
orders for citywide distribution of gas. Unlike the electricity sector, the
Government does not have a problem in gas sector with a vertical monopoly of
the type that Reliance is building. Originally, there was a proposal of a
national gas grid, which would have GAIL as the nodal agency. This also makes
economic sense as whoever owns the gas grid effectively dictates to both the
producers as well as the consumers. That is why generally such facilities are
independently run, with the state playing a crucial role. Unfortunately, all
such policies in the country come a cropper when Reliance is in the picture. So
also with the original gas grid. If we have a gas grid now, it will largely be
a Reliance grid, with GAIL and others playing second fiddle.
We are already seeing the effect of
this monopoly, with Government owned GAIL becoming a junior partner to Reliance
and the transportation cost of $1.25 being charged by Reliance, over and above
the $4.2 and again without any regulatory oversight.
CAG has made clear that the form of
Production Sharing Contract under the NELP is deeply flawed in favour of the
private operators. It provides a perverse incentive to increase capital costs
to the detriment of Government's share of revenue. This is a policy issue that
needs to be urgently addressed in view of the large number of blocks that have
been handed out under NELP.
What does all this mean for the
Indian people? Simply put, we are facing a double loot. On one hand, scarce
national resources are being given away at a pittance. Gas and coal resources
are being handed over to Amabanis, Tatas and sundry others at throw away
prices. However, this is not helping the consumers, who are being asked to pay
international oil and gas prices. Private loot of public resources coupled with
public loot of the consumers – this is the essence of our petroleum policies.
It is indeed welcome that CAG has
drawn attention to the problems in the Production Sharing Contract under the
New Exploration Policy of the Government. However, it is important that other
issues also be addressed, a key one being the pricing of gas. As for the CBI
enquiry against officials who have connived with Reliance, hopefully public
pressure will force a reluctant UPA to act. The only question is will Reliance
be also put on the dock for having subverted the government machinery and
having secured these huge windfalls?
No comments:
Post a Comment